Completed
ocds-adamawa-20...
Drilling of 80m 4” dia upvc casing boreholes and provision of water facilities (installation of 2.0hp grunfos submersible pump, 90m3 (6 x 6 x 2.5m) ex
Total Budget
₦12,001,009
Project Description
Drilling of 80m 4” dia upvc casing boreholes and provision of water facilities (installation of 2.0hp grunfos submersible pump, 90m3 (6 x 6 x 2.5m) existing elevated water tank) for lot (c): government science technical college, mubi
Project Timeline
Planning
Dec 28, 2025Tender
Pending
Award
Awarded to Supplier
Mar 01, 2018Contract
Contract signed
Planning Details
Project planning and budget information
Budget Amount
₦12,001,009
Budget Source
-
Rationale
Tender Information
Procurement tender details and documents
No Tender Information
Tender details have not been added to this project
Involved Parties
All parties involved in the project
No Parties Information
Parties details have not been added to this project
Awards
Project awards and contract assignments
Drilling of 80m 4” dia upvc casing boreholes and provision of water facilities (installation of 2.0hp grunfos submersible pump, 90m3 (6 x 6 x 2.5m) existing elevated water tank) for lot (c): government science technical college, mubi
Award Value
₦11,861,150
Awarded To
Mu’saab Technological Bag LTD
140
Contracts
Contract agreements and modifications
Drilling of 80m 4” dia upvc casing boreholes and provision of water facilities (installation of 2.0hp grunfos submersible pump, 90m3 (6 x 6 x 2.5m) existing elevated water tank) for lot (c): government science technical college, mubi
Contract Value
₦11,861,150
Start Date
Nov 30, -0001
End Date
Nov 30, -0001
Contract ID
ocds-adamawa-2025-041-contract-048
Period
0 days