Completed
ocds-adamawa-20...
Upgrading of ground/elevated water storage tanks by constructing new ones
Total Budget
₦1,415,717,519
Project Description
Upgrading of ground/elevated water storage tanks by constructing new ones
Project Timeline
Planning
Dec 28, 2025Tender
Pending
Award
Awarded to Supplier
Mar 15, 2018Contract
Contract signed
Planning Details
Project planning and budget information
Budget Amount
₦1,415,717,519
Budget Source
-
Rationale
Tender Information
Procurement tender details and documents
No Tender Information
Tender details have not been added to this project
Involved Parties
All parties involved in the project
No Parties Information
Parties details have not been added to this project
Awards
Project awards and contract assignments
Upgrading of ground/elevated water storage tanks by constructing new ones
Award Value
₦1,413,342,332
Awarded To
China Zhonghao (Nig) Ltd
171
Contracts
Contract agreements and modifications
Upgrading of ground/elevated water storage tanks by constructing new ones
Contract Value
₦1,413,342,332
Start Date
Nov 30, -0001
End Date
Nov 30, -0001
Contract ID
ocds-adamawa-2025-077-contract-084
Period
0 days