Rehabilitation of washout section of along Jada-Mbulo Road.
Total Budget
₦200,000,000
Project Description
Rehabilitation of washout section of along Jada-Mbulo Road.
Project Timeline
Planning
Dec 28, 2025Tender
Rehabilitation of washout section of along Jada-Mbulo Road.
Award
Awarded to Supplier
Nov 30, -0001Contract
Contract signed
Planning Details
Project planning and budget information
Budget Amount
₦200,000,000
Budget Source
-
Rationale
Tender Information
Procurement tender details and documents
Rehabilitation of washout section of along Jada-Mbulo Road.
Value
₦0
Procurement Method
Open
Start Date
Jul 07, 2020
End Date
Jul 17, 2020
Tender ID
ocds-adamawa-2025-251-tender-072
Involved Parties
All parties involved in the project
No Parties Information
Parties details have not been added to this project
Awards
Project awards and contract assignments
Rehabilitation of washout section of along Jada-Mbulo Road.
Award Value
₦203,660,250
Awarded To
ATB Barak Services
286
Contracts
Contract agreements and modifications
Rehabilitation of washout section of along Jada-Mbulo Road.
Contract Value
₦203,660,250
Start Date
Nov 30, -0001
End Date
Nov 30, -0001
Contract ID
ocds-adamawa-2025-251-contract-279
Period
0 days