Construction of Theater, Labour Ward and Maternity
Total Budget
₦46,438,218
Project Description
Construction of Theater, Labour Ward and Maternity at Dumne, Song LGA
Project Timeline
Planning
Dec 28, 2025Tender
Construction of Theater, Labour Ward and Maternity
Award
Awarded to Supplier
Jun 16, 2021Contract
Contract signed
Planning Details
Project planning and budget information
Budget Amount
₦46,438,218
Budget Source
-
Rationale
Tender Information
Procurement tender details and documents
Construction of Theater, Labour Ward and Maternity
Value
₦0
Procurement Method
Open
Start Date
Dec 20, 2021
End Date
Mar 20, 2022
Tender ID
ocds-adamawa-2025-329-tender-147
Involved Parties
All parties involved in the project
No Parties Information
Parties details have not been added to this project
Awards
Project awards and contract assignments
Construction of Theater, Labour Ward and Maternity
Award Value
₦53,733,968
Awarded To
R. S. R. Multilinks Investment Ltd
353
Contracts
Contract agreements and modifications
Construction of Theater, Labour Ward and Maternity
Contract Value
₦53,733,968
Start Date
Nov 30, -0001
End Date
Nov 30, -0001
Contract ID
ocds-adamawa-2025-329-contract-426
Period
0 days